Development Planning Act (Cap. 552)
Development Planning Act (Cap. 552), article 72
72. (1) The Planning Board shall have the power to grant or to
refuse a development permission. Any development permission
approved shall be without prejudice to third party rights and shall
not in any manner constitute or be construed as a guarantee in
favour of the applicant as to the title to the property. Moreover in
the granting of a development permission, the Planning Board shall
be entitled to impose such conditions which it may deem
appropriate:
Provided that the Planning Board shall give specific
reasons for any refusal or for any particular conditions that may
have been imposed.
(2) In its determination upon an application for development
permission, the Planning Board shall have regard to:
(a) plans;
(b) policies:
Provided that subsidiary plans and policies shall not be
applied retroactively so as to adversely affect vested
rights arising from a valid development permission, or
a valid police or trading licence issued prior to 1994;
(c) regulations made under this Act:
Provided that the Planning Board shall only refer to
plans, policies or regulations that have been finalised
and approved by the Minister or the House of
Representatives, as the case may be, and published;
(d) any
other
material
consideration,
including
surrounding legal commitments, environmental,
DEVELOPMENT PLANNING
[ CAP. 552.
aesthetic and sanitary considerations, which the
Planning Board may deem relevant;
(e) representations made in response to the publication of
the development proposal; and
(f) representations and recommendations made by boards,
committees and consultees in response to notifications
of applications.
(3) Saving development which in the opinion of the Minister is
of strategic significance or of national interest, related to any
obligation ensuing from a European Union Act, affects national
security or affects the interests of other governments but not
subject to an Environmental Impact Assessment and, or IPPC
matters, the execution and validity of a permit shall be
automatically temporarily suspended and no works as approved by
the said development permit may commence before the lapse of the
time periods established in article 13 of the Environment and
Planning Review Tribunal Act and subsequently will remain so
suspended if the Tribunal so decides in accordance with the
Environment and Planning Review Tribunal Act.
(4) A development permission may be granted for a limited
period but shall cease to be operative if the activity or development
has not been completed within the period specified in the
development permission, if any:
Provided that the Planning Board shall, on the application
of the person holding the full development permission, renew the
said permission on receiving a valid renewal application while the
previous development permission is still operative, to such further
period or periods as it may consider reasonable:
Provided further that where there has been a change in
plans or policies applicable to the requested renewal development
permission, these new plans and policies shall be taken into
account unless the site subject to the application is already
committed by the original development permission in relation to
these plans and policies:
Provided futher that if the applicant fails to submit the
commencement notice relative to the permission, such development
permission shall be considered as never having been utilised.
(5) Any permission still in force shall automatically pass on to
the new owners of the development.
(6) In granting a development permission, the Planning Board
may require the applicant to carry out the activity or development
in stages. The Planning Board shall inform the applicant in the
permission which are the said stages and, following the completion
of each stage, the applicant shall request the Planning Board to
carry out an inspection of the activity or works carried out, and if,
following such an inspection, it is found that the activity or works
have been carried out in terms of the development permission, the
Planning Board shall authorise the applicant to carry out the next
stage of the activity or development.
(7)
Where the Planning Board considers it appropriate to
Cap. 551.
51
52
[ CAP. 552.
DEVELOPMENT PLANNING
closely monitor specific conditions in a development permission by
appointing a person competent for the said purpose, it shall do so at
the expense of the applicant.
(8) Without prejudice to the provisions of this article, where an
application to develop land consists in the mining of minerals, the
Planning Board may and, where planning and environmental
standards so require, shall, require the applicant to provide a
scheme for the treatment of the working and surrounding areas
during the working period and for the treatment of the said areas
when working is completed.
(9) The Planning Board shall not grant permission for the
mining of minerals unless i t is satisfied t hat planning and
environmental standards will be met and that the site will be kept
and eventually left in acceptable conditions.
(10) Where the Planning Board has required a scheme to be
submitted for the various stages as provided in sub-article (6), the
scheme, as accepted by the Planning Board, shall be made a
condition of any permission granted by it, and the Planning Board
shall further require such guarantees to be given by the applicant as
it deems necessary to ensure that the scheme will be adhered to.
Supplementary
provisions
regarding
permissions.